Creating Resilience
Transmission solutions needed for data centers’ renewable energy transition
Which markets are adapting?
May 22, 2023 5 Minute Read
Plans to transition U.S. data centers to renewable energy power sources are impeded by current utility transmission infrastructure. The main problems are outdated power lines, delays in planning and permitting for new transmission and distribution projects and supply chain bottlenecks. Upgrading existing transmission lines can take as long as three years, according to the Lawrence Berkeley National Laboratory, due to time-consuming regulatory hurdles, resulting in multi-million-dollar costs.
Upgrading power transmission infrastructure to accommodate renewable energy sources is a top priority for utility companies. Recently adopted federal legislation provides $2.5 billion in public funding for this effort. Additionally, the Federal Energy Regulatory Commission (FERC) plans to study and address these ongoing issues. Utility companies are cooperating with regulators, city officials, operators and developers throughout the U.S. to improve connectivity.
This report highlights select regional data center markets that are working to advance renewable energy power availability and solve transmission and distribution issues: Northern Virginia, Dallas/Ft. Worth, Silicon Valley and Central Washington. These markets all depend on local renewable energy sources and are at the forefront of a transition necessary for the data center industry to grow on a sustainable basis.
Northern Virginia:
Northern Virginia, the nation’s largest data center market, has historically had low-cost, diverse energy sources. Nuclear power, natural gas and coal collectively represent over 90% of the region’s energy mix.
Regional data center operators and utility providers have been exploring solutions to power transmission and distribution challenges, including upgrading the power grid and increasing renewable energy sources. Dominion Energy, the area’s utilities provider, will support key customers’ sustainability goals and renewable energy objectives outlined in the Virginia Clean Economy Act. This act mandates that Dominion Energy produce 100% renewable electricity by 2045.
To help meet this goal, Dominion Energy’s Integrated Resource Plan includes over 5,000 MW of offshore wind, over 14,000 MW of solar and 2,700 MW of storage available by 2037. It will spend $7 billion in “Electric Grid Transformation” expenses for transmission, grid transformation and strategic undergrounding to ease transmission and distribution bottlenecks. $22 billion is earmarked for offshore wind, solar, nuclear reactor life extensions and energy storage.
Figure 1: Northern Virginia Fuel Mix
Source: Dominion Power.
Figure 2: Northern Virginia Historical Vacancy Rates
Source: CBRE Research, CBRE Data Center Solutions, H2 2022.
Dallas/Ft. Worth:
Dallas/Ft Worth remains a top location for data center development, recently surpassing Silicon Valley as the nation’s second-largest data center market. Plentiful power supply is a key contributing factor. 299.4MW is currently under construction as of H2 2022, a 25% year-over-year increase.
The region is traditionally known for its oil and gas production, but recent wind and solar development have meaningfully diversified the energy supply mix. Texas now produces about 26% of all U.S. wind-powered electricity. Oncor, Dallas/Ft. Worth’s main utility provider, has connected over 2,000 MW of renewable power to ERCOT, the State of Texas’s independent energy grid.
Upgrading power lines is essential for new data centers because of their large power demands, and regional regulations are addressing this need. Texas Senate Bill 1281, passed in 2021, grants new transmission line projects under three miles the right to proceed without the previously required certificate of convenience and necessity (CCN). The prior exception maximum was one mile.
Additionally, ERCOT offers the State of Texas advantages for improving power transmission and distribution. ERCOT’s repairs, upgrades and other work can be executed much more quickly because there is no formal bidding process available to outside companies. Oncor is offered right of first refusal on projects involving its power lines, such as transmission upgrades or rebuilding.
Figure 3: Dallas/Ft. Worth Fuel Mix
Source: EIA.
Figure 4: Dallas/Ft. Worth Historical Vacancy Rates
Source: CBRE Research, CBRE Data Center Solutions, H2 2022.
Silicon Valley:
Silicon Valley was the U.S.’s second-largest data center market prior to H2 2022, but is now the third-largest. The presence of major technology companies including Google, Facebook and Apple significantly contributed to the market’s growth, particularly in Santa Clara, where most of the region’s data centers are now located.
This region has experienced power generation issues due to incredibly high demand for commercial, residential and data center digital infrastructure. On the transmission side, many substation sites will not be energized until 2028-2029 and their timing for coming online may be delayed due to the grid capacity being maxed out in Santa Clara.
Silicon Valley Power (SVP), Santa Clara’s municipal utility provider, is making improved power generation a top priority to address these challenges. SVP has committed to eventually procure new energy only from renewable and/or greenhouse-gas-free sources: 50% renewable energy by 2026, 60% renewable energy by 2030 and greenhouse gas-free supply by 2045. An early adopter of wind power, SVP began investing in wind farms in the early 1980s. Today, SVP generates hydroelectric and solar power across California and Washington.
Despite delays in bringing on new substations, Silicon Valley remains an attractive data center market. Vacancy hit a historic low of 1.3% in H1 2022, rising to 2.3% in H2 2022. Under-construction activity reached an all-time high of 141.6MW in H2 2022, up from 100.6MW in H1 2022.
Figure 5: Silicon Valley Fuel Mix
Source: Silicon Valley Power.
Figure 6: Silicon Valley Historical Vacancy Rates
Source: CBRE Research, CBRE Data Center Solutions, H2 2022.
Central Washington:
This region is particularly advantaged due to its hydroelectric power supply, which accounts for 55% of its electricity generation. The large hydro contribution results in one of the U.S.’s cheapest power rates ($0.028 to $0.035 per kW) and has attracted developers and hyperscalers.
However, this surge in activity has caused the regional power supply in Grant County to approach capacity. Plans for 230 kV infrastructure upgrades and a new 230 kV transmission line are underway to increase system reliability and provide incremental capacity to data centers in Grant County. The upgrades are expected to be completed by H2 2028.
Grant PUD, the local utility provider in Quincy, WA, is evaluating additional and new forms of carbon-free generation. This includes:
- Nuclear energy via small, modular reactors
- New hydrogen and solar power plants
- Additional wind power plants
Figure 7: Central Washington Fuel Mix
Source: Washington State Department of Commerce.
Figure 8: Central Washington Historical Vacancy Rates
Source: CBRE Research, CBRE Data Center Solutions, H2 2022.
Related Services
Optimize your data center real estate with worldwide consulting, advisory and transaction, project management an...
Zero from CBRE is here to help your business realize its sustainability commitments, in the most pragmatic and cost-effective way possible.
Contacts
Insights in Your Inbox
Stay up to date on relevant trends and the latest research.